The scope of the project was to construct several high voltage and distribution rooms across various floors of the building, for the acceptance of a new high voltage feed into the building.
The work consisted of asbestos abatement in various types of materials, structural and architectural construction, housekeeping pads, high voltage feed and distribution gear installations, electromagnetic shielding of all transformer rooms, mechanical and HVAC installations, epoxy flooring systems and other cosmetic finishes.
The project was completed in 2 phases, where in the first phase the rooms were built and in the second all equipment was installed and commissioned.